Dalkia, Canadian fund Fengate Capital Management to develop 40-MWe biomass power plant in Fort St. James, British Columbia, that will consume 307,000 tonnes of biomass/year, mostly waste from local forestry industry

Allison Oesterle

Allison Oesterle

PARIS , November 15, 2013 (press release) – Dalkia and Canadian fund Fengate Capital Management Ltd. will develop one of Canada's largest biomass plants which will be designed, built and operated by Dalkia in Fort St. James, British Columbia.

Dalkia and Fengate Capital Management Ltd. have closed the financing for this state of the art biomass plant. Under this DFBOM (Design, Finance, Build, Operate and Maintain) contract, Dalkia will operate and maintain the facilities and manage the wood biomass supply and preparation.

Funding for this project, one of the largest in Canada and North America, will be provided by the Canadian fund Fengate Capital Management Ltd. leading an international pool of banks. Dalkia and Fengate Capital Management Ltd. have contracted Iberdrola Engineering & Construction to build the plant.

With an electricity capacity of 40 MW, this new plant will consume 307,000 metric tons of biomass a year. Dalkia will manage the biomass supply working closely with local forestry companies, sawmills and the First Nations. The biomass used by this plant will largely comprise waste from the British Columbia forestry industry, such as sawmill and logging waste, and trees killed by the mountain pine beetle epidemic that has ravaged British Columbia forests over past ten years.

This plant will generate electricity sold to BC Hydro & Power Authority to power almost 40,000 Canadian households. It will avoid the annual discharge of around 95,000 metric tons of CO2 - the equivalent of more than 45,000 cars off the road.

The project will also create around 250 jobs during the construction phase, and then 80 new direct and indirect jobs during the 30-year operation period.

Franck Lacroix, Chairman of Dalkia

"This project will capitalize on Dalkia's worldwide experience in designing and operating more than 450 biomass plants. In winning this contract, Dalkia has demonstrated its know-how and expertise, and the relevance of its international growth strategy. Dalkia and Fengate Capital Management Ltd. are together finalizing an identical biomass power plant in Merritt, British Columbia."
 

This project will generate for Dalkia cumulative operating and biomass sales of more than €600 million over the contract's 30-year term.

Dalkia will operate the coming biomass plant in Fort Saint James


Click here to see full press release.

* All content is copyrighted by Industry Intelligence, or the original respective author or source. You may not recirculate, redistrubte or publish the analysis and presentation included in the service without Industry Intelligence's prior written consent. Please review our terms of use.

Share:

About Us

We deliver market news & information relevant to your business.

We monitor all your market drivers.

We aggregate, curate, filter and map your specific needs.

We deliver the right information to the right person at the right time.

Our Contacts

1990 S Bundy Dr. Suite #380,
Los Angeles, CA 90025

+1 (310) 553 0008

About Cookies On This Site

We collect data, including through use of cookies and similar technology ("cookies") that enchance the online experience. By clicking "I agree", you agree to our cookies, agree to bound by our Terms of Use, and acknowledge our Privacy Policy. For more information on our data practices and how to exercise your privacy rights, please see our Privacy Policy.