Metsa Fibre's bioproduct mill project in Kemi, Finland, is advancing on schedule, moves to installation phase; 1,300 workers are on site, most pile driving is complete, work on pipe and conveyer foundations, power lines is progressing

Sample article from our Bioeconomy

KEMI, Finland , March 29, 2022 (press release) –

​The construction of the bioproduct mill is advancing on schedule. Nearly all the pile driving has now been completed, and work on the pipe and conveyor foundations is progressing. The installation of concrete elements is well advanced in many areas including the pulp mill and the debarking and kiln drying departments. Ground slabs and foundations for equipment and tanks are being laid in many areas, including in the turbine building and at the evaporation plant.

Mechanical installations are underway at the digester, the impregnation vessel and the large bleached pulp towers. The steel structure of the recovery boiler is rising and equipment installations have begun. The installation of tanks, pumps and bleach plant washers continues at the pulp mill and the causticising.

The frame for the Ajos port warehouse is now under construction, and the installation of facade and ceiling elements continues. By now, the port warehouse in Ajos is distinguishable in the web camera stream.

Foundation work for the 110 kV power line poles has been completed, and more than half the poles are now in place. The power line will supply electricity from the bioproduct mill to the national grid.

Around 1,300 people work daily on the bioproduct mill site.

Electrical automation and ICT work will begin this spring

Having the best partners in the field is of great importance in a large-scale construction project. At present, around 150 companies are working towards a common goal on the site.

The partners for the electrical automation and ICT projects, vital to bioproduct mill operations, were recently selected, and installations will begin later this spring. 

“We require all our partners to commit to the project’s safety, schedule and quality goals. The partners we chose represent these values and have undertaken to observe them with us,” says Jari-Pekka Johansson, Director of the bioproduct mill project.

Editor's Note: A video update for the mill project can be found at Metsä Fibre’s website by clicking here.

* All content is copyrighted by Industry Intelligence, or the original respective author or source. You may not recirculate, redistrubte or publish the analysis and presentation included in the service without Industry Intelligence's prior written consent. Please review our terms of use.

See our dashboard in action - schedule an demo
Jason Irving
Jason Irving
- SVP Enterprise Solutions -

We offer built-to-order bioeconomy coverage for our clients. Contact us for a free consultation.

About Us

We deliver market news & information relevant to your business.

We monitor all your market drivers.

We aggregate, curate, filter and map your specific needs.

We deliver the right information to the right person at the right time.

Our Contacts

1990 S Bundy Dr. Suite #380,
Los Angeles, CA 90025

+1 (310) 553 0008

About Cookies On This Site

This website stores cookies on your computer. These cookies are used to improve your website experience and provide more personalized services to you, both on this website and through other media. To find out more about the cookies we use, see our Privacy Policy. We won't track your information when you visit our site. But in order to comply with your preferences, we'll have to use just one tiny cookie so that you're not asked to make this choice again.