US government's year-long moratorium on installing 20,000 communication antennas has delayed implementation of Positive Train Control, which now will be only 20% complete by 2015 deadline; industry has spent US$4B so far on PTC: AAR

Cindy Allen

Cindy Allen

WASHINGTON , April 17, 2014 (press release) – $4 Billion Spent to Date to Implement High-Tech Braking System

In a new report updating the industry’s progress on installing Positive Train Control (PTC), the nation’s freight railroads said that a year-long moratorium on installing 20,000 communication antennas imposed by the Federal Communications Commission (FCC), followed by a lengthy federal approval process mandated by the agency, has seriously delayed the implementation of nationwide interoperable PTC. Whereas freight railroads once projected that by 2015 they would have PTC installed on 40 percent of the network mandated by FRA, they now believe thanks to the FCC issues only 20 percent of the PTC network will be up and running by the Congressionally imposed deadline.

“Everyone in the industry is greatly frustrated at the inability to move forward and do what we need to do to advance PTC installation,” said Association of American Railroads President and CEO Edward R. Hamberger. “It’s been two steps forward, three steps back for months and we simply don’t have the certainty we need to move ahead and get PTC tested, fully functioning, certified and ready to go.”

Causing the timing for installation to be delayed significantly, Hamberger said, was an FCC directive to suspend installation of approximately 20,000 communications antennas necessary to for PTC to work until the antennas are assessed through the FCC’s environmental and historical evaluation process. The problem, Hamberger noted, is that how the thousands of antennas are to be reviewed has yet to be determined. The majority of the antennas at issue are between 10- to 60-feet tall, and roughly 97 percent are located on railroad property, he added.

The freight rail industry is expected to install PTC on approximately 60,000 miles of mainline track and has spent approximately $4 billion to date implementing the automatic braking system Congress called for as part of the 2008 Rail Safety Improvement Act.

AAR’s report to FRA summarizing the freight railroad industry’s progress, available here, includes an in-depth look at issues, such as delays in availability of critical back-office-server software, complexities of mapping an ever-changing nationwide rail network, and taking a phased approach to testing and implementing PTC on each railroad’s PTC network.

Hamberger noted that despite the challenges, railroads so far have been able to make progress in some areas of PTC implementation, including:

Installing or partially installing PTC equipment on 50 percent of the locomotives on which it will be required;
Deploying one third of the wayside units that will be required;
Replacing half of the signals needed for implementation, and
Mapping most of the track that will be equipped with PTC.


# # #

For more information contact AAR Media Relations: media@aar.org, or 202-639-2345.

About AAR: The Association of American Railroads (AAR) is the world's leading railroad policy, research and technology organization focusing on the safety and productivity of rail carriers. AAR members include the major freight railroads of the U.S., Canada and Mexico, as well as Amtrak. Learn more at www.aar.org. Follow us on Twitter: AAR_FreightRail or Facebook: www.facebook.com/freightrail.

* All content is copyrighted by Industry Intelligence, or the original respective author or source. You may not recirculate, redistrubte or publish the analysis and presentation included in the service without Industry Intelligence's prior written consent. Please review our terms of use.

Share:

About Us

We deliver market news & information relevant to your business.

We monitor all your market drivers.

We aggregate, curate, filter and map your specific needs.

We deliver the right information to the right person at the right time.

Our Contacts

1990 S Bundy Dr. Suite #380,
Los Angeles, CA 90025

+1 (310) 553 0008

About Cookies On This Site

We collect data, including through use of cookies and similar technology ("cookies") that enchance the online experience. By clicking "I agree", you agree to our cookies, agree to bound by our Terms of Use, and acknowledge our Privacy Policy. For more information on our data practices and how to exercise your privacy rights, please see our Privacy Policy.